![]() | ||
Case Studies : IPE Costs Comparison |
Introduction A study was conducted comparing the IPE cost estimate of an actual design versus the cost estimate of the equipment sized by IPE. Although IPE allows the user to manipulate the design criteria and the parameters of the sized equipment, these values were left as the default, to compare the cost of the default against the actual design. IPE Functionality In addition to equipment, the other project components include plant bulks, site development i.e. demolition, drainage, earthwork, fencing, landscaping, roads, piling and railroads, and any buildings involved in the process or for off-site use. In developing the piping, instrumentation, civil, steel, and electrical designs, IPE takes into account the plot area, process complexity, the soil conditions and the required power distribution and process control systems. An in-built P&ID library is used to determine the piping and instrumentation requirements for each item of equipment. The stream flows and conditions are used to size the pipes, and to select the pipe schedules and insulation requirements. The plot area is used to determine the pipe, electrical cabling/wiring and instrument signal wiring/tubing lengths. The soil conditions and placement of equipment i.e. on grade, pad or in a structure, influences the civil and structural design. Based on the generated design, IPE determines the capital investment cost, the project schedule for basic engineering design through construction to plant start-up, operating costs and also performs an investment analysis. Capital costs are reported as direct costs and indirect costs. Direct costs include materials and labour to install the process equipment, bulk materials for installation of process and off-site equipment, plant bulks, power distribution and process control network components, buildings and site development. Indirect costs include basic and detailed engineering, procurement, field supervision, construction equipment rental, commissioning and start-up costs. Case Study The process facility equipment comprised one trayed distillation column, three centrifugal pumps, six shell and tube heat exchangers and two horizontal drums. The IPE default material of construction is Carbon Steel, and since MOC has a large effect on cost, the MOC of applicable equipment and piping was changed to stainless steel. The resultant capital cost estimate for the two cases is summarised in Table 1. Table 1: IPE Capital Cost Comparison for Two Equipment Sizing Cases
|
Most of the IPE sized equipment items are different to the actual and this results in the difference in cost. The draw-off and bottoms pump were not included in the Aspen simulation and were manually entered in Case 2, hence the cost estimate for these two items was the same. Reasons for the variations in cost are as follows:
Sensitivity Analysis Table 3: Breakdown of Material Costs
The pipe sizes selected by IPE in Case 1 were smaller than the actual pipe sizes. The calculated pipe lengths were the same in all three cases since the defined plot area was the same. These pipe lengths were not manually changed in Case 3 as the plot layout has not yet been allocated or defined. The number of control valves was reduced for Case 3, resulting in a decrease of instrumentation costs. The insulation were also reduced for Case 3, since IPE used the input temperatures to determine the insulation requirements, and the user enter the design temperatures which are much higher than the operating temperatures. Conclusion and Recommendations IPE offers the flexibility to change the default design criteria as well as many of the calculated parameters. This allows the user to change the equipment/ piping/ instrumentation data as the design develops to improve the accuracy of the cost estimate. In this case, by entering known piping and instrumentation data the total cost increased by just over 1%, but the material costs spread between the different accounts is more accurate. The specification of exotic materials has a great impact on cost. Therefore it is recommended that the user change the carbon steel default to the required MOC. Also, the user should also check installed sparing requirements on rotating equipment as the IPE default is to install only one item. IPE is an excellent tool for generating order of magnitude estimates. It is important that the user checks that the data generated by the program meets the site requirements. For semi-definitive estimates, the IPE data can be exported to ICARUS, which allows cost estimators the flexibility to adjust all variables to generate a comprehensive cost estimate. |
A case study from AVEC - adding value through innovation |