| Year |
Client |
Project |
Country |
| 2009 |
Nehawu |
Lake Kivu Pre-Feasibility |
DRC |
| Pre-feasibility study for Methane gathering from Lake Kivu and further processing options |
| 2009 |
VGI |
Review of Shaka Airport Design |
South Africa |
| Process review of design for Jet Fuel Storage |
| 2009 |
VGI |
Secunda - Natref Pipeline |
South Africa |
| Process support for concept and basic engineering |
| 2009 |
VGI |
Alrode Fuel Depot |
South Africa |
| Process support for concept and basic engineering |
| 2009 |
Sastech / Sasol |
Solvents Growth NAC Handling |
South Africa |
| Conceptual engineering to provide alternatives for handling NAC's |
| 2009 |
CabGOC |
PHA / HAZOP Studies |
Angola |
| HAZOP facilitator and scribe for a number of offshore platforms |
| 2009 |
United National Breweries SA |
Technical Review of Sorghum Breweries |
South Africa |
| Technical Assessments (Operations and Maintenance) of 5 Breweries for Nedbank and Client |
| 2008 |
African Energy Resources Ltd |
Chirundu JV Project |
Zambia |
| Owner's team project management and technical assistance for a uranium project |
| 2008 |
E+PC / MagMinerals Inc. |
Kouilou Potash Project |
Republic of Congo |
| Bridging works for BFS development for a new potash project |
| 2008 |
LMDC |
Various as-built's |
Lesotho |
| Various drawing and "as-built" works for diamond processing plant |
| 2008 |
MMR |
Gas Recovery |
Rwanda |
| Basic engineering for the prototype gas
(methane) recovery system for Lake Kivu |
| 2008 |
CabGOC |
IHAZID Risk Assessment and Evaluation - Aviation and
Medical |
Angola |
| IHAZID facilitator and scribe
services |
| 2008 |
CabGOC |
IHAZID Risk Assessment and Revaluation - Malongo Camp,
Logistics and Well Servicing Operations |
Angola |
| IHAZID facilitator and scribe
services |
| 2008 |
CabGOC |
PHA/HAZOP Studies |
Angola |
| For a number of off-shore platforms and
on-shore facilities |
| 2008 |
Worley Parsons Pangaea |
HAZOP-NMPP Projects |
South Africa |
| HAZOP facilitator and scribe services for
the new multi-products pipeline project |
| 2008 |
GRD Minproc |
HAZOP - Platinum Concentrator |
South Africa |
| HAZOP facilitator and scribe services for
a new platinum concentrator project |
| 2007/8 |
Sastech |
U29 / 229 |
South Africa |
| As building of Secunda U29/229 in order
to establish baseline documentation to support growth project |
| 2008 |
Monitor, Russia |
Evaluation of Refinery Assets and Investment
Opportunity |
Russia |
| Economic and technical pre-feasibility of
refinery options |
| 2008 |
IPG |
New Petroleum Products Terminal and Storage
Facilities |
Mozambique |
| Conceptual engineering and design for a
new petroleum storage terminal |
| 2008 |
CabGOC |
IHAZID Risk Assessment and Evaluation - Terminal and
Drilling Operations |
Angola |
| Risk assessment facilitation and scribe
services |
| 2008 |
Impala Platinum |
Peer Review |
|
| Review and audit of the capital cost
estimates for the PMR Phase IV Expansion project |
| 2008 |
VGI / ACSA |
Additional Jet Fuel Facilities for OR Thambo
Airport |
South Africa |
| Basic engineering for new bulk storage
facility and operating philosophy of existing facility |
| 2008 |
Sastech / Sasol |
Value Added Projects |
South Africa |
| Various eg. Refinery optimization,
product recovery improvement |
| 2007 |
Sastech |
Solvents Utilities |
South Africa |
| As building of Secunda solvents utilities
in order to set scope for concept development |
| 2007 |
Worley Parsons Singapore |
Refinery, Tank Farm and Distribution |
Zimbabwe |
| Study of existing refinery, terminal and
distribution facilities |
| 2007 |
Sastech |
Simulation Modeling |
South Africa |
| Simulation modelling of U35/235
operations to correct existing models |
| 2007 |
PGBI |
Gas Recovery |
Rwanda |
| Concept development for the prototype gas
recovery system for Lake Kivu |
| 2007 |
VGI |
Multi-Products Pipeline and Storage |
Mozambique/ South Africa |
| Concept design and development for the
pipeline, off-loading and storage for a new multi-products petroleum
pipeline |
| 2007 |
Sastech |
Solvents Unit Baseline |
South Africa |
| U37 solvents hydraulics and baseline
study |
| 2007 |
CabGOC |
IHAZID |
Angola |
| IHAZID investigation of the Kuito
offshore facility |
| 2007 |
VGI |
Compressors |
South Africa |
| Compressor study and costing evaluations
for gas pipeline |
| 2007 |
VGI/ACSA |
New Aviation Jet Fuel Tank Farm |
South Africa |
| Conceptual and basic design for a new jet
fuel tank farm at OR Thambi airport |
| 2007 |
Sastech |
Propane Vaporiser |
South Africa |
| Propane vaporiser basic engineering |
| 2007 |
Sastech |
Solvents Unit Baseline |
South Africa |
| U38/238 solvents hydraulics and baseline
studies |
| 2007 |
Worley Parsons |
Terminal, Multi-Products Pipeline and
Storage |
Mozambique/Malawi |
| Concept design and engineering for a new
multi-products petroleum pipeline and storage facilities |
| 2007 |
Ivanhoe Platinum |
Bankable Study |
South Africa |
| Compilation of a 43-101 document for
bankable feasibility |
| 2007 |
Impala Platinum |
Peer Review |
South Africa |
| Peer review of design and capital cost
estimates for plant expansion |
| 2007 |
Sastech |
Flare Troubleshooting |
South Africa |
| Troubleshooting of Turbo and PP2 flare
systems |
| 2007 |
CabCOG |
PHA for On-Shore Operations |
Angola |
| PHA (Process Hazard Analysis) for the
on-shore terminal and topping plant |
| 2007 |
CabCOG |
IHAZID |
Angola |
| IHAZID investigations of the Takula, EK
and NN off-shore facilities |
| 2007 |
Sastech |
Concept Engineering for Refinery Unit |
South Africa |
| U29 concept engineering for the Synfuels
growth project |
| 2007 |
Sastech |
Concept Engineering for Phenosolvan |
South Africa |
| Concept development for the phenosolvan
pumps |
| 2007 |
Sastech |
Naphtha Injection |
South Africa |
| Tie in package compilation for the
naphtha injection project |
| 2006 - 2007 |
MAGMinerals |
Kouilou Potash Project |
Republic of Congo |
| Providing Consultancy Services to
MAGMinerals Inc on their Bankable Feasibility Study |